Khaf – Herat railway contractor

Iranian company Ballast describes itscontract for work on the Khaf – Herat railway project in an undated article on its website:

Client: Construction and Development of Transportation Infrastructure Company
Type of Contract: PC
Contract Period: 9 months
Location: Razavi Khorasan Province

Project Outline
The east corridor of country is a railway which begins from Chabahar port and through Dogharoun connects to Afghanistan, Kyrgyzstan and China railway networks. Khaf-Sangan-Harat is a part of east corridor which is 191 km long. 2 parts of this rail lines are in Iran’s territory and 2 parts are located in Afghanistan. Considering the location of Sangan ore mine in Khaf, a major part of ore is being transported through this railway so development of railway from Khaf toward southern parts of country is considered as one of the government principle programs in this field. From international perspective since Afghanistan is a country gifted with many minerals, particularly the extension of Sangan mine, importance of using railway system as to reach to the open water highlighted. Khaf-Harat railway project, which is a single line with 76.8 km length stats from 24th km of Sangan-Torbat Heydarieh railway and from the 55th, is located along the border and at 78+800 reaches Shamtigh border point. This railway is designed based on axial load of 25 tons and 160 km/h speed.

Scope of Work
The project’s scope of work includes supply of equipment & materials, construction and installation works, laying rails.

Key Statistics

Laying rail: approximately 90 km
Station improvement: 5
Turnout: 54
Ballast: approximately 224000m3
Sleepers: approximately 150000
Rail: approximately 11000 tons

Source: Khaf-Harat Laying Rail Project, Ballast Manufacturing & Infrastructure, Iran