President Berdimuhamedov inspects construction of TAT railway

Map of the Turkmenistan - Afghanistan - Tajikistan railway project

President of Turkmenistan Gurbanguly Berdimuhamedov reviewed the construction of the Turkmenistan – Afghanistan – Tajikistan railway during a working visit to Lebap velayat, Turkmenistan: the Golden Age reports.1

He travelled from Turkmenabat Airport by helicopter to Ymamnazar (or Immamnazar, or various other spellings), “where construction of Atamyrat – Ymamnazar – Akina – Andhoy steel line undergoes at full pace”. At Ymamnazar received reports about the customs facilities which handle Around 250 – 300 trucks per day, then visted an hydrocarbon terminal where “construction is at the final stage”. The terminal includes a “Railway loading rack for hydrocarbons”.

He then went to the future Ymamnazar station. As of the date of the visit, 85 km of earthworks had been built on the Atamyrat – Ymamnazar line, 82.2 km “filled with sand and gravel mixture”, 82 km of rails had been laid and a road parallel to the railway had been prepared. The earthworks on the Afghan sectioon of the railway to Akinoy “is prepared”, and construction works at two Gulistan and Ymamnazar stations “are at the final stages”.

“This railway is summoned to become the road of friendship and cooperation of the countries of the region and reliable transport main. Realization of this project, besides economic benefits, will open wide opportunities for integration of participating countries into the international economy at equal partnership.”
Turkmenistan: the Golden Age

Deputy Chairman of Cabinet of Ministers S Satlykov and Minister of Transport B Annameredov provided the president with information about the railway project. The President “expressed his interest in rates and quality of construction works at other parts of the railway”, and “emphasized that deadline for putting into operation of the railway are important requirements for construction of this complex engineering and technical infrastructure”.

During his return flight to Turkmenabat the President saw the work underway on two bridges on the Atamyrat – Ymamnazar – Akina railway. These bridges are 5 m wide, with the bridge at the 15 Years of Independence lake being 256m long and the bridge over the Karakum River being 363 m long. Construction of the reinforced concrete piers has been completed, and temporary piers and metalwork are being installed.

“Successful realization of the construction project of this strategic transport corridor will provide not only further steadfast social and economic development of Lebap region but the whole Turkmenistan as well. As it was mentioned above, the right bank of the Amudarya River has unique deposits of natural reserves. Establishment of reliable railway connection will serve as key factor of rapid development of this countless treasury.”
Turkmenistan: the Golden Age

I can’t seem to find any photos of this presidential trip, but I suspect there might be some out there somewhere – do let me know if you spot any!

References

Turkmenistan – Afghanistan railway under construction

45 km of the Atamyrat (formerly Kerki) to Ymamnazar (Imamnazar) section of the Turkmenistan – Afghanistan – Tajikistan railway had been laid as of June 30, Turkmenistan: the Golden Age reported on 30 June 2015.

Construction of the line was ceremonially launched on 5 June 2013. In January 2014 it had been reported that the 85 km section could be completed by June 2015.

Turkmenistan – Afghanistan rail link to be completed in June 2015

On 10 January 2014 The Times Of Central Asia reported that “Additional forces were sent for construction of Atamyrat-Imamnazar (85 km) site of Turkmenistan-Afghanistan-Tajikistan railway“, citing Altyn Asir (Golden Age) TV.

The report says completion had been planned for the end of 2016, but has now been brought forward to June 2015. The 400 km route between Atamurat, Imamnazar, Aqina, Andkhoy, Panj and Tajikistan “will be implemented by 2015”